15 College Terrace, Brighton

Four-level Victorian terrace in Kemp Town · Strip-out, damp and mould treatment, lime plastering throughout · Eight original sash windows restored

Initial condition

A Victorian terrace with failing linings, mould in the top floor and tired sashes

No. 15 College Terrace is a four-level Victorian terraced house in Brighton's Kemp Town. The original lath and plaster wall linings had reached the end of their life through the hallway and stairs, the living room and all three top-floor bedrooms, and the bedroom ceilings were in a similar state. The top floor also showed established mould growth, and one internal wall of the living room was carrying damp. Eight original timber sash windows survived but had been painted over for decades, with failed putty and softened timber at the meeting rails and cills.

The brief was to take the house back to sound structure and bring it up in the right materials: breathable lime plaster rather than gypsum, and repair of the existing sashes rather than replacement.

Diagnosis before finishes

Strip out first, then look at what the structure is doing

Everything came off before anything went on. Stripping the lath and plaster and taking down the bedroom and mid-level ceilings exposed the joists and rafters for inspection, which is the only reliable way to know what a lining has been hiding. One bedroom's ceiling joists needed sistering; a supporting steel was introduced across the rear top-floor bedroom; and the mould-affected surfaces were cleaned, treated and neutralised and allowed to dry before any boarding or plaster went near them. The damp living room wall had its defective plaster removed and the cause addressed before it was re-plastered in lime, so the wall can continue to dry out rather than being sealed. This is the sequence we describe in our damp and moisture work: understand the moisture first, then choose the finish.

Repair approach

Lime throughout, and eight sashes restored rather than replaced

Ceilings and timber stud walls were counter-battened and boarded to give a true substrate, then the house was lime-plastered from the living room up through every hallway and stairwell level to the top-floor bedrooms and bathroom. The rear external wall of the top back bedroom was insulated internally and boarded before plastering. Each of the eight sash windows was stripped to bare timber, repaired with two-part wood filler with unsound sections replaced, shellac-primed, re-glazed in linseed-oil putty and finished with a full undercoat and topcoat system. Alongside the fabric work, the old kitchen was removed, hot and cold supplies and a new waste run under the floor, and the bathroom stripped, refitted and tiled.

Outcome

A structurally sound, mould-free house with breathable lime finishes on every wall, its original sash windows retained and working, and new kitchen and bathroom services in place. The work was carried out in itemised, fixed-price stages agreed in advance, with each stage completed and settled before the next began.

Scope of works

What was carried out

The works were agreed as itemised, fixed-price stages across three agreements — the main renovation, the additional strip-out and structural items, and the kitchen and rear-wall works — and are set out here in the order they were carried out.

Phase 1 — Clearance and strip-out

Everything came off before anything went on, so the structure could be inspected rather than guessed at.

1Stage 1

Waste clearance

Removal of all household waste, furniture and contents from the property before works began, with same-day off-site disposal.

2Stage 2

Remove lath and plaster — hallway and stairs, four levels

Careful removal of the lath and plaster wall linings on all four stair and hallway levels, bagged, stacked and removed for off-site disposal, using access equipment where the ceiling heights required it.

3Stage 3

Remove lath and plaster — three top-floor bedrooms

Strip-out of the old lath and plaster wall linings across all three top-floor bedrooms, carried out as controlled demolition to minimise dust and protect the remaining structure.

4Stage 4

Remove lath and plaster — living room, high ceiling

Removal of the existing lath and plaster from all living room walls, with access equipment for the high ceiling.

5Stage 5

Remove ceilings — three bedrooms

Safe removal of the ceiling coverings in all three bedrooms under dust control, exposing the joists and rafters ready for inspection.

6Stage 6

Remove mid-level ceiling

Strip-out of the mid-level ceiling covering and associated debris, with protection of the surrounding areas and disposal of all materials.

7Stage 7

Remove kitchen

All kitchen units, worktops, fittings and appliances disconnected, safely removed and disposed of responsibly. The living room was serving as the kitchen at the time.

8Stage 8

Remove bath, basin, WC and tiles

Existing sanitaryware and wall tiles carefully removed from the bathroom, leaving clean, clear surfaces for reinstallation.

Phase 2 — Moisture, mould and structure

With the fabric exposed, the moisture and structural problems were dealt with before any new lining went in.

9Stage 9

Mould and damp treatment — three top-floor bedrooms

Mould-removal and damp treatments applied to the affected surfaces; areas showing growth cleaned, scrubbed and neutralised, with a final assessment to confirm the mould had been effectively removed.

10Stage 10

Making good the damp wall — living room, internally

Defective plaster removed from the damp-affected wall and the area treated, then re-plastered in a breathable lime system so the wall can dry rather than being sealed.

11Stage 11

Sister ceiling joists — one bedroom

New timbers fixed alongside the existing ceiling joists in one bedroom to restore stiffness and give a sound fixing for the new ceiling.

12Stage 12

Install supporting steel joist — top-floor rear bedroom

A steel joist installed bearing onto the brickwork across the internal side of the top-floor rear bedroom to carry the structure above.

Phase 3 — Substrate, insulation and boarding

True, stable backgrounds were built before plastering.

13Stage 13

Counter-batten three bedroom ceilings

Battens fixed across the joists in all three top-floor bedrooms to level the ceilings and provide a fixing grid for boarding.

14Stage 14

Board three bedroom ceilings

Plasterboard fixed to the counter-battened ceilings in all three bedrooms.

15Stage 15

Counter-batten timber walls — two bedrooms, both sides

Timber stud partitions in two bedrooms counter-battened on both faces to give a flat, sound background.

16Stage 16

Board timber walls — two bedrooms, both sides

Plasterboard fixed to both sides of the counter-battened stud walls in the two bedrooms.

17Stage 17

Insulate rear wall — top-floor rear bedroom

Insulation installed to the internal face of the rear external wall in the top-floor back bedroom, improving thermal performance without altering the elevation.

18Stage 18

Board rear wall — top-floor rear bedroom

Plasterboard fixed over the insulated rear wall ready for lime plaster.

Phase 4 — Lime plastering throughout

Breathable lime plaster was used in every room, finished smooth and ready for decoration.

19Stage 19

Prep and plaster three bedroom ceilings

The newly boarded ceilings in all three top-floor bedrooms prepared and plastered.

20Stage 20

Plaster top-floor left bedroom — lime

Walls of the top-floor left bedroom plastered in breathable lime.

21Stage 21

Plaster top-floor right (front) bedroom — lime

Walls of the top-floor right front bedroom plastered in breathable lime.

22Stage 22

Plaster bedroom at top of stairs (right) — lime

Walls of the bedroom at the top of the stairs plastered in breathable lime.

23Stage 23

Plaster living room — lime

All living room walls plastered in breathable lime, including the made-good damp wall.

24Stage 24

Plaster bathroom — lime, walls and ceiling

Bathroom walls and ceiling plastered in lime, finished breathable and ready for paint or tile.

25Stage 25

Plaster hallways and stairways — all levels, lime

Lime plaster applied across every hallway and stairwell wall on all four levels, finished breathable and cohesive from top to bottom.

Phase 5 — Sash window restoration, eight windows

Living room (two), bedroom near the living room, top-floor right front bedroom, bathroom, bedroom at the top of the stairs, hallway and stairs, and top-floor left front bedroom. Every window was repaired rather than replaced.

26Stage 26

Strip eight sash windows

All paint, varnish and coatings removed from frames and sashes to expose clean timber ready for repair and priming.

27Stage 27

Repair eight sash windows

Holes, cracks and defects filled with two-part wood filler; any missing or unsound timber replaced; repairs sanded and profiled flush.

28Stage 28

Prime eight sash windows

Shellac-based primer applied to all exposed and repaired timber to seal the surface and stabilise it against moisture, giving strong adhesion for the finishing coats.

29Stage 29

Replace glazing putty — eight windows

Defective putty removed and glass rebates cleaned, then re-glazed in new linseed-oil putty for a breathable, weather-resistant seal.

30Stage 30

Paint six sash windows

Full undercoat and topcoat system applied to the living room (two), top-floor right front bedroom, bathroom, top-of-stairs bedroom and hallway windows. The two remaining bedroom windows were left primed for the client to finish.

Phase 6 — Kitchen services and bathroom

New services were run while the floors and walls were open.

31Stage 31

Hot and cold plumbing / sub-floor

Floorboards lifted in the affected area, new hot and cold pipework and fittings installed, and the floor boarded back over.

32Stage 32

Waste pipe installation

New waste pipe installed to serve the kitchen.

33Stage 33

Install bath, basin and WC

New sanitaryware installed with all fixings and connections and tested for watertight performance.

34Stage 34

Tiling

Wall and floor tiles laid to the specified layout, grouted and sealed for a waterproof finish.

Placeholder: Safe-Bricks photography — 15 College Terrace

Stripped lath and plaster and exposed joists, mould treatment on the top floor, counter-battened ceilings, lime plastering in progress, and the restored sash windows before and after.

First step

Not sure where to start?

Send us photographs of the area of concern. It is the most straightforward first step — we will look at what you can see and advise on the appropriate next steps.

Send Us Photographs